Saturday 30 January 2010

The tiles are up and we can see how much brighter the room is going to be.















Thursday 28 January 2010

New bath fitted

The walls have all now been plastered and the bath partly installed. 3 downlighters with dimmer installed. At last we can start to see how much of better space it will be.






















Wednesday 27 January 2010

Bye bye to the old avocado suite....








Hmmmm, lovely old suite...










New shower bath going against this wall













New pipework being laid under floor



This wall was pulled down and put back up again, 5cms further back so we could get a full size 1700mm bath in.








Most of the plaster fell off against this wall, so its all been ripped back.





Today we had the old bathroom ripped out. So long to the 1970s avocado suite. Works are expected to take 7-10 days and as you can see most of the plaster fell off so we're having to have it completed replastered. More pics to follow.